Six things schedulers actually do all day — then a look inside the sandbox, rendered by the same CPM engine that runs the app. No signup, nothing to install.

STEP 1 · EDITING

Edit like a spreadsheet

Click a cell and type — Enter commits and moves down, Tab moves right, and pasting a block from Excel lands cell-by-cell from the active cell, mapping columns across like Excel does. The fill handle drags "Area 01" into Area 02, Area 03… Every edit is one Ctrl+Z of 100 levels.

#Task nameDurationQuantity
7Storm drain — Area 014d220 LF
8Storm drain — Area 024d180 LF
9Storm drain — Area 03 ← fill handle continues the series4d
STEP 2 · DEPENDENCIES

Link the logic

Predecessors read exactly like you learned them: 12, 12SS, 12FF, 12FS+3d, comma-separated. The Successors column mirrors automatically — type 14SS+2d on task 5 and task 14 gains the complement. Insert or delete rows and every reference renumbers itself, because links live on stable task identities underneath.

TaskPredecessors
Cure deck11
Open lane12FS+3d
+3d lag
STEP 3 · CPM

Constraints, float & the critical path

All four MS Project constraint types, an independent deadline diamond, and a full backward pass: Late Start, Late Finish, Total and Free Float. Negative float shows red everywhere — grid, Gantt, exports. Widen the critical threshold to catch near-critical work before it goes critical.

Total float −3d — a Finish-No-Later-Than the chain can't meet, red in the grid, the Gantt and every export.
STEP 4 · BASELINES

Baselines & variance

Snapshot the plan at award, keep up to five named baselines, and draw any of them as gray bars under the live schedule. Start Var and Finish Var columns use the MS Project sign convention — positive slipped red, negative ahead green — and rows that slip get a red row number.

gray = "Award baseline"
TaskStart VarFinish Var
Drilled shafts+3d+3d
Pier caps−1d−1d
STEP 5 · UPDATES

Status the month

One dialog sets the data date and records per-task actuals, with "on plan" shortcuts for the easy ones. Completed work anchors at its actual dates, in-progress work resumes no earlier than the data date with retained logic, and the whole round is one Ctrl+Z. The blue data-date line draws on the Gantt and in PDFs.

Status update — data date Jul 13, 2026
Drilled shaftsstarted on plan60%
Pier capsnot started0%
Unstarted work reschedules from the data date · retained logic · one Ctrl+Z undoes the whole round
STEP 6 · SUBMITTALS

Prove it to the owner

A one-click, 13-point schedule-quality audit adapted from the DCMA assessment: missing logic, leads, lags, hard constraints, high float, negative float, stale progress and more. Thresholds are editable and stored per project. Click a failing check to jump to the offenders, then export the letterhead PDF report that survives email.

Schedule health — 11 of 13 checks pass
Missing logic✓ 0%
Leads (negative lag)✓ 0
High float > 44d✗ 9.6%
Negative float✓ 0
DCMA-style thresholds, editable per project · letterhead PDF report for the submittal

The sandbox

A real bridge-replacement schedule through the real CPM engine — exactly as the app draws it.
Critical chain in red — a full backward pass behind it FS links with lag drawn between bars Summary bars roll up their phases Hover a bar for its dates & float
SR-12 Bridge Replacement Active
✓ Saved just now You (demo)
# Task name Dur Start Finish Predecessors %
1 Preconstruction 0 (ms) Jun 1 Jun 22 0%
2 Notice to Proceed 0 (ms) Jun 1 Jun 1 100%
3 Submittals & permits 10d Jun 1 Jun 12 2 100%
4 Mobilization 5d Jun 15 Jun 19 3 100%
5 Substructure 0 (ms) Jun 22 Jul 30 0%
6 Cofferdam & excavation 8d Jun 22 Jul 1 4 100%
7 Drilled shafts 12d Jul 2 Jul 17 6 60%
8 Pier caps 8d Jul 20 Jul 29 7 0%
9 Superstructure 0 (ms) Jul 30 Aug 21 0%
10 Set girders 6d Jul 30 Aug 6 8 0%
11 Deck pour & cure 10d Aug 7 Aug 20 10 0%
12 Finishes 0 (ms) Aug 21 Sep 7 0%
13 Rails & approach slabs 7d Aug 21 Aug 31 11 0%
14 Striping & punchlist 4d Sep 1 Sep 4 13 0%
15 Substantial completion 0 (ms) Sep 7 Sep 7 14 0%
Jun '26 Jul Aug Sep
Submittals & permits
Mobilization
Cofferdam & excavation
Drilled shafts
Pier caps
Set girders
Deck pour & cure
Rails & approach slabs
Striping & punchlist
15 tasks · critical path 70 working days · finish Sep 4, 2026 Sample schedule — the live app is one trial away
Like the look of it? The real thing is fully live — plus calendars, statusing, costs, health checks, imports and your whole team. Start your 14-day trial Read the cheat sheet →