Ganttry GANTTRY

See it work.

Learn six common scheduling tasks, then try them in the demo below. It uses the Ganttry app. No signup or install needed.

STEP 1 · EDITING

Edit like a spreadsheet

Click a cell and type — Enter commits and moves down, Tab moves right, and pasting a block from Excel lands cell-by-cell from the active cell, mapping columns across like Excel does. The fill handle drags "Area 01" into Area 02, Area 03… Press Ctrl+Z to undo an edit. You can undo up to 100 steps.

#Task nameDurationQuantity
7Storm drain — Area 014d220 LF
8Storm drain — Area 024d180 LF
9Storm drain — Area 03 ← fill handle continues the series4d
STEP 2 · DEPENDENCIES

Link the logic

Predecessors read exactly like you learned them: 12, 12SS, 12FF, 12FS+3d, comma-separated. The Successors column mirrors automatically — type 14SS+2d in task 5's Successors cell, and task 14 gets predecessor 5SS+2d. Insert or delete rows and every reference renumbers itself, because links live on stable task identities underneath.

TaskPredecessors
Cure deck11
Open lane12FS+3d
+3d lag
STEP 3 · CPM

Constraints, float & the critical path

Four constraint types: SNET, MSO, FNLT and MFO. SNET, start no earlier than, is an earliest-start limit: the task can start later but never sooner. MSO, must start on, pins the start exactly. FNLT, finish no later than, moves nothing but shows negative float with a red warning when the finish lands late. MFO, must finish on, moves nothing but warns whenever the finish is not exactly on that date. There is also an independent deadline diamond and a full backward pass: Late Start, Late Finish, Total and Free Float. Negative float shows red everywhere — grid, Gantt, exports. Widen the critical threshold to catch near-critical work before it goes critical.

Total float −3d — a Finish-No-Later-Than the chain can't meet, red in the grid, the Gantt and every export.
STEP 4 · BASELINES

Baselines & variance

Snapshot the plan at award, keep up to five named baselines, and draw any of them as gray bars under the live schedule. Start Var and Finish Var columns use the MS Project sign convention — positive slipped red, negative ahead green — and rows that slip get a red row number.

gray = "Award baseline"
TaskStart VarFinish Var
Drilled shafts+3d+3d
Pier caps−1d−1d
STEP 5 · UPDATES

Status the month

One dialog sets the data date and records per-task actuals, with "on plan" shortcuts for the easy ones. Completed work anchors at its actual dates, in-progress work resumes no earlier than the data date with retained logic, and the whole round is one Ctrl+Z. The blue data-date line draws on the Gantt and in PDFs.

Status update — data date Jul 13, 2026
Drilled shaftsstarted on plan60%
Pier capsnot started0%
Unstarted work reschedules from the data date · retained logic · one Ctrl+Z undoes the whole round
STEP 6 · SUBMITTALS

Prove it to the owner

A one-click, 13-point schedule-quality audit adapted from the DCMA assessment: missing logic, leads, lags, hard constraints, high float, negative float, stale progress and more. Thresholds are editable and stored per project. Select a failed check to find the affected tasks. Then export a PDF report with your letterhead.

Schedule health — 11 of 13 checks pass
Missing logic✓ 0%
Leads (negative lag)✓ 0
High float > 44d✗ 9.6%
Negative float✓ 0
DCMA-style thresholds, editable per project · letterhead PDF report for the submittal

Try it right here.

This is the real Ganttry build, running privately in your browser — nothing you do here is uploaded, and a refresh resets the sandbox.

The real app — same build, same CPM engine Import your own XER / MS Project XML / CSV / Excel (first 60 tasks) Edits live only in this browser — refresh to reset Exports & saving unlock with the free trial
Sample — Office Building Demo
Task NameDur
▾ Preconstruction20d
◆ Notice to Proceed0
Permits & approvals15d
▾ Sitework25d
Clear & grub5d
Mass excavation10d
▾ Foundations34d
Footing excavation8d
ScheduleWorkCalendar

On a phone the demo opens in Ganttry's mobile view — the same live sandbox, sized for the field. The editing tour above shines on a laptop; the mobile side is all yours to try:

Open the live demo →
~3 MB first load · nothing to install · a refresh resets the sandbox
Like the look of it? The real thing is fully live — plus calendars, statusing, costs, health checks, imports and your whole team. Start your 14-day trial Read the cheat sheet →